This article covers the steps to generate a shared link view for a Cintoo project. This link grants view-only access to the whole work zone structure of a project without a specific camera position.
Permissions: users with roles including Share permission in project root work zone can share a project.
- Go to My Projects.
- On any project, click Share icon either on a project card or on the map context menu to open Create panel along the right-hand side.

- Name: allows to identify the share link among others. Browser tab shows this name followed by project name. See more Share Link Explorer.
- Require the user to be a member (disabled by default): by enabling this option, only members who have been added to the Cintoo project can open a share link. User has to authenticate.
- Password (enabled by default): set a password to control who can open a share link.
Password must be at least 12 characters long and contain at least 3 of the following: uppercase, lowercase, digit, special characters. - Set expiration date for URL (enabled by default): expiration date will be set to 14 days from date of share link creation by default unless changed or disabled.
- Select the resources to share: at least one of the following options must be enabled before creating a share link:
- Work zones: (enabled by default)
- Notes: (enabled by default)
- Issues: (disabled by default)
- Measurements: (enabled by default)
- Crops: (enabled by default)
- Tags: (disabled by default)
- Include your company logo (optional): allows to add a JPEG or PNG branding image to a share link. Logo will be embedded at the bottom left-hand corner in 3D View.
- Click Create.

A green Project Share pop-up window appears on the bottom right of the screen. Click on View to have the link opened in a new browser tab titled with link name followed by project name. Click on Copy link to save the link to share in any convenient way.
All links for projects are stored in Share Link Explorer in root work zones.

Was this article helpful?
That’s Great!
Thank you for your feedback
Sorry! We couldn't be helpful
Thank you for your feedback
Feedback sent
We appreciate your effort and will try to fix the article