Using Work Zones

This article describes how to use work zones that separate data into different folders, for example by phasing, date captured, work areas etc.


1. In Work Zone Explorer select root project folder or a specific work zone to be displayed in 
3D View.



2. Use Work Zone Explorer to toggle on/off other work zones to be displayed in 3D View by checking the checkboxes next to work zones.


3. Use Resource Explorer to toggle on/off various work zones and individual data files contained within each work zone in 3D View.